– Third Phase: Termination process –

As of May 19, the third phase has already begun, without losing the continuity of the other phases.

In detail:

  • Zone A: The 3rd phase has begun, with the reconsideration of the houses, the placement of the metal profiles of the partition walls and the placement of the fences and sub-frames for the windows.
  • Zone B: Still in the first phase of the concrete structure, the basement floor has already been executed, with the SPA pools and it is ready to concrete the ground floor, and this phase is expected to be finished within this month of May , to then assemble the wooden structure during the month of June.
  • Zone D: The 2nd phase of the wooden structure is being completed with the placement of the roof panels.
  • Zone C: The wooden structure is well advanced with the 3rd floor finished