– First stage: land containing –
Residencial Altavista disembarks in Andorra, starting the project “Arbres del Tarter“.
Arbres del Tarter, an exceptional location in Andorra, is a high-end multifamily building with all kinds of details. Exclusivity, the highest quality, nature and a careful design unite in this location. It is a development with 49 unique apartments in which you can enjoy the mountain, nature, and sports. The construction project will be performed in 3 stages. During this period, we will inform and document the location of each one of them.
The construction project has started at the beginning of September 2022, the perimeter screen walls with micropiles have been executed, and the plot has been excavated until the level, where the first stage of the anchorages will be performed.
– First stage: foundations –
Arbres El Tarter is progressing in the first stage. As of October 20, 2022, progress has been made in the following steps:
- At zone A, the excavation has reached the foundation level and the filtering gravel has been spread on the ground. On top of this, a concrete cleaning layer has been placed and, on top of it, the waterproofing membrane. From there, construction of the foundation slab will begin.
- At zone B, the excavation is 70% complete and the access ramp to the construction site is located there.
- At zones D and C, the anchoring of the micropile screen continues, and the excavation is 90% complete.
On the other hand, the tower crane necessary for the execution of the work has already been installed.
Arbres El Tarter evolves in the first stage. On 3 November 2022, there has been progress in the following steps:
- In the A zone, scrap has been placed, the foundation slabs have been concreted and the formwork of the pillars at the floor -2 has started.
- In the D zone, the gravel extension and the execution of the cleaning concrete layer have started.
- We have finalized the execution of the micropiles screen with their corresponding anchorages.
- Almost all the plot has been dug, except for the access ramp to the works of the B zone.
– First stage: foundation, walls and slabs –
Arbres El Tarter evolves in the first stage. On 18 November 2022, there has been progress in the following steps:
- In the A zone, we have risen the pillars, and we have made the formwork of the roof of the basement -2, and we are placing the scrap to concrete the next Monday 21 November.
- In the D zone, we have placed the waterproofing layer.
- In the B and C zones, we have extended the drainage gravel, and the cleaning concrete layer has been executed.